8.9.2.2 — September 2026
Phases
- Phase 7 complete — every workload now runs on the new virtualisation platform, and the old one is gone.
- Phase 8 begins — platform maturity, with six workstreams opening together: delivery gates, GitOps standardisation, secret management, onboarding, notifications and remote access.
Services
- Released and documented an internal certificate authority replacing ad hoc self-signed certificates for internal infrastructure.
- Released a self-hosted remote-support tool for helping family and friends with their Windows PCs, with pre-configured installers ready to hand out.
Stability
- Fixed nearly 500 GB of storage on the virtualisation hosts that was allocated but holding nothing, restoring headroom on both disk pools.
- Retrofitted the last machine still carrying the old platform's guest tooling, completing the switch across every workload.
Tracks in this release: Phases · Services · Stability
Shipped Features
1
Nearly 500 GB of allocated-but-empty storage reclaimed on the virtualisation hostsComplete1
Guest tooling migration completes across every workloadComplete2
Phase 7 — Migration out of VMwareComplete1
Phase 8 — Platform maturityIn Progress1
An internal certificate authority replacing self-signed certsComplete1
Self-hosted remote support tool for family and friendsComplete